Shaft 2 Backbone Services, Stage 1

Scope of services included preparing and establishing a selection of Shaft 2 surface facilities that are required to allow development of C2S, shaft sinking and equipping to commence (pipeline installation around the Shaft 2 area, underground construction warehouse extension and electrical installation).

267 manpower, 208,500 man hours, 1,125 m3 earthworks, 10 t steel structures, 1,337 m electrical network and 4,281 m plumbing network